There is an old Turkish proverb that says "the forest was shrinking, but the trees kept voting for the axe." Whether intended or not, it captures something of the contradiction at the heart of Turkey's energy story. Solar power has become the country's cheapest source of electricity, decisively undercutting domestic coal generation. Yet Turkey's own National Energy Plan projects electricity's share of total energy to reach just 24.9% by 2035, up from 21.8% in 2020 — a figure that sits awkwardly alongside the country's COP31 proposal championing a global 35% electrification target by the same year.
The numbers tell a story of ambition and tension in equal measure. Official capacity targets stand at 30 GW for solar and 18 GW for wind, whilst the newly discovered Sakarya gas field is projected to cover up to one-quarter of annual national demand. For a country simultaneously positioning itself as a clean energy advocate on the world stage and quietly banking on domestic gas reserves, the gap between rhetoric and roadmap is hard to ignore.
What emerges is not a simple tale of green ambition. Turkey's renewable pivot is driven by economics as much as climate conviction, shaped by geography, and complicated by the kind of energy politics that rarely make it into official press releases. The potential is real. So are the implementation challenges.
The headline figures are striking. Wind and solar now generate more than one-fifth of Turkey's total electricity supply, a share that would have seemed optimistic just a decade ago when the country's grid was heavily anchored to imported gas and coal. Wind capacity has exceeded 14 GW, concentrated initially along the Aegean and Marmara coastlines where private sector developers moved early and fast. Solar has since surpassed 24 GW of installed capacity, its growth trajectory shaped by a different set of forces entirely.
The two technologies followed distinct paths. Wind expanded first, propelled by favourable coastal geography and private investment appetite. Solar took longer to gather momentum, but once regulatory changes in 2017 made distributed generation more accessible, the pace quickened considerably. What followed was remarkable even by the standards of fast-moving renewable markets: capacity doubled in just 2.5 years, climbing from 9.7 GW in July 2022 to over 19 GW by the close of 2024. Turkey's 2025 solar target of 18 GW was surpassed roughly 1.5 years ahead of schedule. As renewable capacity expands, a green energy recruitment agency can help employers identify professionals with the technical expertise needed to support the next phase of development. The driver behind 94% of this growth was not utility-scale development but installations built primarily for self-consumption — businesses and households choosing energy independence over grid reliance.
Taken together, renewables now represent 57% of Turkey's total installed capacity. When hydropower, geothermal, and biomass are included alongside wind and solar, clean energy sources account for approximately 43% of actual electricity generation. Fossil fuels still provide more than half of what the grid delivers at any given moment — a reminder that installed capacity and reliable output are not the same thing.
The government's stated ambition is to more than triple existing wind and solar capacity by 2035. Whether the economics, the infrastructure, and the political will align to make that happen is the more interesting question.
Before examining where Turkey is heading, it is worth understanding what is pushing it there. The country imports 74% of its energy needs, a structural exposure that creates an annual bill ranging between TRY 2,244 billion and TRY 2,799 billion. Energy imports account for roughly 20% of total imports, making them, as researchers have noted, the primary driver of Turkey's chronic current account deficit. Put simply, every time global energy prices spike, Turkey feels it more acutely than almost any comparable economy.
The dependency runs deep. Turkey imports 100% of its natural gas, 91% of oil products, and 77% of coal. That is not an energy mix with a weak spot — it is an energy mix that is almost entirely exposed to external price shocks and geopolitical disruption. Studies have found that whilst renewable energy has a disinflationary effect in its own right, the compounding benefit of reduced import dependency is even more powerful in containing inflation. The domestic economy, in other words, has a direct stake in how quickly Turkey can generate its own power.
The crises of recent years have driven this point home with considerable force. The Russia-Ukraine conflict pushed Turkey's energy trade deficit to a record TRY 2,799.83 billion in 2022, up from TRY 1,463.78 billion just a year earlier in 2021. More recently, following the Hormuz Strait closure in February 2026, Turkey's energy import bill surged by TRY 483 billion through May alone — a 26% increase in a matter of months. These are not abstract macroeconomic statistics. They represent real fiscal pressure on a country already managing significant inflation.
The economics now point clearly in one direction. Solar LCOE currently sits at 25 USD/MWh, compared to the marginal cost of imported coal at 73 USD/MWh. New wind and solar capacity costs less to build than it does to keep existing imported coal plants running. Combined with Turkey's net zero 2053 commitment, the case for accelerated renewable deployment is less a matter of green idealism and more a matter of financial common sense.
So what does the plan actually look like? The National Energy Plan sets a headline figure of total installed capacity reaching 189.7 GW by 2035, with renewables accounting for 64.7%. That alone would represent a substantial step forward. However, Turkey did not stop there. The October 2024 Renewable Energy Roadmap raised the stakes considerably, targeting 120 GW of combined wind and solar capacity — a 45% increase over the previous 82.5 GW goal. Hitting that target requires 6-7 GW of new capacity additions annually through competitive auctions, a pace that is ambitious but not without precedent given the solar deployment rates already recorded.
The investment picture matches the scale of the ambition. Turkey plans approximately TRY 6,904.63 billion in total energy transition financing by 2035, with TRY 2,761.85 billion of that earmarked specifically for grid modernisation, transmission expansion, and system flexibility. Infrastructure commitments include 14,700 km of new HVDC transmission lines and 40 GW of additional transmission capacity. These are not peripheral additions — they are the backbone without which any capacity target remains theoretical.
On the regulatory side, the YEKA auction mechanism continues to drive large-scale deployment, targeting 2 GW of annual allocations. Recent amendments to the framework have introduced three particularly noteworthy changes: a "super permit" initiative cutting project approval timelines from 48 months to under two years, transmission fee exemptions for qualifying projects, and minimum feed-in tariffs of USD 4.95 per kWh for initial years. Reducing the approval timeline alone could prove transformative. Historically, lengthy permitting processes have been as much a barrier to deployment as financing constraints.
As project requirements evolve with permitting decisions and development timelines, contingent recruitment can provide an additional route to sourcing specialist talent when hiring needs arise.
Storage integration deserves particular attention. Battery capacity targets reach 7.5 GW by 2035, whilst 33 GW of storage-integrated projects currently sit in the pre-licence pipeline — a figure that suggests considerable private sector confidence in the direction of travel. The World Bank is supporting grid digitalisation through SCADA and energy management system upgrades, which will be critical to managing the variability that comes with a grid increasingly dominated by wind and solar. Getting storage and grid infrastructure right is, in many respects, the decisive question. The capacity targets are achievable. Whether the system can absorb and distribute that capacity reliably is where the real work lies.
Turkey's story is ultimately one of economic necessity meeting genuine opportunity. The renewable pivot is not primarily a climate story — it is a response to a structural vulnerability that has quietly undermined the Turkish economy for decades. When solar costs less than half the marginal cost of imported coal, and when energy dependency accounts for a fifth of all national imports, the case for renewables writes itself.
The ambition embedded in the October 2024 Roadmap is substantial. Reaching 120 GW of combined wind and solar by 2035 will require consistent delivery on grid modernisation, storage integration, and regulatory simplification — all simultaneously. The "super permit" initiative and the YEKA auction framework are encouraging signals, but policy intent and project execution are two very different things. History in the energy sector suggests that the gap between the two is where ambitious targets tend to quietly disappear.
That said, there are genuine grounds for optimism. Turkey has already demonstrated it can move fast when the conditions are right — solar capacity doubling in under three years was not an accident, it was the result of supportive regulation and a private sector ready to respond. If that same momentum can be channelled into large-scale storage and transmission infrastructure, Turkey's greatest economic liability could, within a decade, become one of its most significant competitive assets.
The pivot is real. Whether the execution matches the roadmap is the question worth watching.